Monitoring the construction of a СHP in the Sovetskaya Gavan town | ССИ Инжиниринг

Monitoring the construction of a СHP in the Sovetskaya Gavan town

On December 25, 2019, the boiler unit of station No. 1 was kindled with diesel fuel to the pressure of 60 atm for steam blowing of steampipes.


In March this year, it is planned to kindle the boiler unit st. No. 1 on coal and the first start-up of the steam turbine No. 1.


The completion of the project is scheduled for September 30, 2020.


On the project “Construction of a СHP in the Sovetskaya Gavan town”, JSC “SSE Engineering” provides engineering services with banking support for the construction of electric power facilities in the Far East.

​​​​​​​